Why tradespeople should record site delays
The practical case for recording site delays: better conversations, fairer pricing, protection against disputes and a clearer picture of where your time goes.
By the TradeProof team · Updated · 4 min read

Most tradespeople shrug off delays as part of the job. Recording them takes seconds, and pays off in several ways.
1. Conversations start from facts
"We lost about three hours across the week" is easy to dispute. A dated list of delays with reasons is much harder to argue with, and usually keeps the discussion polite.
2. You price more accurately
If a particular client, agent or site type regularly causes delays, the records show it. You can then add contingency, change your terms or decide whether to take that work.
3. You are protected if blamed
Sometimes a delay is wrongly attributed to you. A record made at the time, with photos, shows what was happening.
4. You may be able to recover costs
Where your contract allows for delay costs or extensions of time, notice and evidence are often required. Records made at the time are the foundation. Check your contract's notice provisions.
How to make it a habit
- Record delays the same day, while the details are fresh.
- Keep each entry short: when, what, who you told.
- Use a single place, such as TradeProof or the site delay template.
Not legal advice. This is general information for UK tradespeople. Contract terms and consumer rights depend on the circumstances; for a significant dispute, speak to a solicitor, your trade body or Citizens Advice.