How to document waiting time on construction sites
Practical ways to record time lost waiting on site, from access and other trades to materials, so that delay conversations start from facts.
By the TradeProof team · Updated · 5 min read

On site, waiting rarely feels significant in the moment, but an hour lost here and there adds up. Documenting it turns a vague complaint into a clear record.
What counts as waiting time
- Waiting for access, keys or a site induction.
- Waiting for another trade to finish or clear an area.
- Waiting for materials, a decision or a drawing.
- Waiting for utilities to be isolated or reconnected.
What to record
- When you were ready to start, and when you could actually start.
- What you were waiting for, stated factually.
- Who you told, how and when.
- A photograph showing the situation, such as the blocked area.
- Whether you could do other useful work meanwhile. If you could, count only the time you genuinely lost.
Keep it factual
Write what happened, not whose fault it was. "Waiting for plasterers to vacate first-floor rooms, 09:10 to 10:25. Told site manager at 09:15" is stronger than "plasterers held us up again".
Tools
The TradeProof waiting timer saves the start time so it stays accurate if the app closes. On paper, use the site delay report template. Cost it with the waiting time calculator.
Whether delay costs can be recovered depends on your contract. Check what it says about delay, extensions of time and notice requirements, as some require written notice within a set period.
Not legal advice. This is general information for UK tradespeople. Contract terms and consumer rights depend on the circumstances; for a significant dispute, speak to a solicitor, your trade body or Citizens Advice.