Recording additional work outside the original scope
How to record and agree extra work found during a job, so changes in scope and price are clear before you carry on.
By the TradeProof team · Updated · 6 min read

Rotten timber behind a bath panel, an old wiring fault, a wall that is not plumb: jobs change once you open things up. Agreeing changes before you do the work avoids the most common payment disputes.
Stop, record, agree
- Stop before doing extra work that was not agreed.
- Record the original agreed work, what you found and why more is needed, with photos.
- Price the additional work clearly, including materials and time.
- Agree it with the customer before proceeding, in writing: a message or email is usually enough.
What the record should show
- Original scope and price.
- The additional work and the reason.
- Estimated extra cost.
- Customer approval status: not requested, requested, approved or declined.
If the customer declines
Record that too, and what that means for the job (for example, "left as found; customer informed of risk"). If you cannot complete the work safely, say so.
Why the paper trail matters
Under the Consumer Rights Act 2015, a price that was not agreed in advance must be reasonable. Agreeing in advance removes the argument.
TradeProof has an Additional work record type for exactly this. See costs versus charges.
Not legal advice. This is general information for UK tradespeople. Contract terms and consumer rights depend on the circumstances; for a significant dispute, speak to a solicitor, your trade body or Citizens Advice.